AWAKEN THE FUTURE SCHEDULE:

Monday, Oct 8: Construction Prep Begins (fencing installed, materials/equipment begin arriving)
Sunday, Oct 14: Groundbreaking Event after AM gatherings (no parking in front of warehouse, additional parking available at North Ave/Elm St lot)
Monday, Oct 15: Construction Begins
Sunday, Oct 21: Cafe/Warehouse Buildings Unavailable
(temporary Restrooms/Cafe space in use)
Friday, April 19, 2019: Property Complete (Furniture + Equipment installed)
Sunday, April 21, 2019: Easter Sunday (All buildings/spaces in use)

construction parking plan-01.jpg

PLAN OVERVIEW.

CLICK THE IMAGE BELOW TO ENLARGE.


PROPERTY IMPROVEMENTS.

  • Improved walkability and covered walkways

  • Increased connection and training spaces

  • Increased office and meeting spaces will allow staff to work from this property during the week

  • Designed as a multi-purpose space for outreach and city events during the week

  • Kidtown building will house a licensed child care center during the week

  • Auditorium capacity will increase from 500 to 1000 seats

  • Increased number of restrooms connected to Auditorium and alternate meeting rooms

  • Current Auditorium space will become available for future development

PROJECT COSTS.

Renovation Design + Fundraising: $400,000

Construction: $3,250,000

Site Improvement + Courtyard: $800,000

Fixtures, Finishes, and Equipment: $650,000

Project Total: $5,100,000

PROJECT TIMELINE.

Design + Permitting: August 2017 — October 2018

Construction + Site Work: October 2018 — Spring 2019